Press Release
ISSUE UPDATE
OWOSSO (COUNTY) DRAIN PROJECT
Status Report
Background
The City petitioned
the Shiawassee County Drain Commissioner in 1997 for Improvements to the
Owosso (County) Drain to address flooding in the southwest quadrant of
Owosso. This drain serves a watershed of about 3500 acres with about 25%
being in the City of Owosso, about 75% in Owosso Charter Township and
just a small area in Bennington Township. The existing drain was found
to be inadequate and in need of improvement. However, the magnitude of
the project and proposed sharing of the improvement cost, led to
litigation and several years delay. The engineering was completed and
construction bids were finally taken in May 2001. The cost to be
apportioned was set at $3.37 million. A Board of Review heard challenges
to the assessment roll prepared by the County Drain Commissioner in late
2001. Subsequently, four appeals were filed with the Circuit Court
challenging the assessments and seeking to stop, or reduce the scope of,
the project. This litigation has now been settled and the project,
somewhat reduced in scope and cost, will begin in 2005.
What will be done?
About 5,700 feet of
72” diameter concrete storm sewer will be installed from just north of
Milwaukee St. (between Cedar and Chipman) to the southwest along the
railroad right-of-way to south of South Street. This relief drain will
route the majority of the storm flows from the watershed south and west
of the City of Owosso to the mainline section of the former Comstock
Drain that has excess flow capacity. The new 72-inch drain will relieve
the existing, overburdened 54-inch drain that will remain in service
primarily serving the City area. The 72-inch relief drain will have
about four times the flow capacity of the existing 54-inch drain. There
will be an inlet control structure on the 54-inch drain to allow it to
accept excess flows from the south, but only up to the carrying capacity
of the pipe.
Initially, the
project included construction of a major (56 acre-feet of storage) storm
water detention facility and improvements to the open drain and various
culverts south of South Street, past Dewey Road, past Delaney Road, and
all the way to Hibbard Road. The detention facility and open drain
improvements were deleted from the project scope to settle the appeals
brought in 2001, particularly that of Owosso Charter Township.
What is the construction schedule?
The Drain
Commissioner has signed the construction contract with Zito Construction
and has issued the Notice to Proceed. The contractor will begin limited
clearing and preparation work beginning the week of January 17th
while pipe is being produced. They project beginning excavation and pipe
installation in early March working from near Milwaukee Street southwest
toward South Street along the railroad right-of-way. The schedule calls
for substantial completion by the end of July and final completion by
the end of August 2005.
What is the project
cost and how is it financed?
Preliminary project
costs of $478,000 were assessed against the drainage district in 2002.
The September 2004 “computation of costs” to complete the project
totaled $2,341,000. County Drain Bonds in the amount of $2,265,000 were
sold in December to finance these remaining project costs. Note that the
portion of the project costs paid by the State for highway drainage is
prepaid and not included in the Bond financing. The Bond repayment will
be over 20 years to 2025 at an average interest rate of 4.11%.
The $2,341,000
remaining project costs will be assessed to the drainage district in
accordance with the Assessment Roll certified by the Board of Review on
January 30, 2002. That assessment will begin with the winter tax bill
issued in December 2005 for City residents in the drainage district.
There was NOT an assessment for the Owosso Drain project on the 2004
Winter Taxes.
A portion of the
project costs will be paid “at-large”; City of Owosso 8.72%; Shiawassee
County 7%; Owosso Charter Township 6.12%; MDOT (state) 2.83%; and 1.74%
to railroads. The remainder is assessed to property owners in the
drainage district. The City will also be assessed about 4.7% for certain
properties it owns in the district.
How much will the
assessments be to landowners?
Assessment amounts
will vary based on parcel size and land use. For a standard city lot
(66’x132’ or 0.2 acres) and residence, the assessment amount would be
about $550. A double lot (0.4 acres) with a single residence would be
about $650. Commercial, industrial or multi-family uses are assessed at
a higher rate since they generally have greater impervious surface
coverage and greater run-off rates. Vacant and agricultural lands have
lower per acre assessment factors.
Property owners will
likely have the option to pay the full assessment in the late fall or to
have the assessment spread over twenty years. For a total assessment
amount of $600 to be spread over 20 years with interest, the amount due
with next winter’s taxes would be on the order of $60 ($30 principle and
about $30 interest for the first year). Subsequent annual amounts would
decrease as the interest charge declines as the assessment principle is
paid down. Please note these figures are for illustration. The County
Drain Office will determine the actual final assessment roll, payoff
policies and interest rate.
Will the
improvements eliminate flooding in southwest Owosso and flood insurance
requirements for properties currently in the “100-year” flood hazard
zone?
The project will
significantly reduce, but will not totally eliminate, flooding in
southwest Owosso. The 72-inch relief drain was designed to handle the
runoff from a “10-year” storm event. The retention basin was designed to
reduce peak runoff rates from a 25-year storm event, but that portion of
the project will not be constructed. However, the need for the retention
basin is reduced by also eliminating upstream open drain improvements.
It will be important to maximize on-site retention requirements for any
new developments in the upper portion of the watershed.
We expect a
significant reduction, but not elimination, of the 100-year flood hazard
area in southwest Owosso. An updated hydraulic analysis of the watershed
will be required for the Federal agency to delineate a revised flood
hazard zone and flood insurance requirements.