PROJECT STATUS REPORT
2022-2024 Water Service Line Replacement Project
Work scope includes noncompliant water service line replacements targeting 600 locations within the City of Owosso over a 3-year time period. The project is complete. A total of 676 water service lines were replaced as part of the project.
2023 Street Patch Program
Work scope includes patches on various streets within the city of Owosso needed for water main breaks, sewer repairs, etc. The project is complete.
Safe Routes to School Project (2024)
Work scope includes constructing ADA compliant sidewalk ramps at various locations within the city along with constructing new sidewalks primarily in the Middle School area. The project is complete.
Stewart Street Reconstruction Project (2024)
Stewart Street from Shiawassee St (M-52) to Washington St: Work scope includes pavement reconstruction with curb and gutter replacement, storm sewer replacement, ADA sidewalk ramps, select sidewalk replacement, and permanent pavement markings and signing; water main replacement. The project is a MDOT Small Urban Program project with the water main portion approved as part of the State of Michigan Department of EGLE 2024 Drinking Water State Revolving Fund project. The project is complete with punch list and closeout procedures underway.
2024 Water Main Replacement Project
1. Dewey Street from Brandon to Moore: Work scope includes water main replacement including non-compliant water service line replacement. The project was approved as part of the State of Michigan Department of EGLE 2024 Drinking Water State Revolving Fund project. The project is complete with punch list and closeout procedures underway.
2. Grace Street from Cedar to Shiawassee: Work scope includes water main replacement including non-compliant water service line replacement. The project was approved as part of the State of Michigan Department of EGLE 2024 Drinking Water State Revolving Fund project. The project has been postponed due to funding.
3. Tracy Street from Frederick to Stewart: Work scope includes water main replacement including non-compliant water service line replacement. The project was approved as part of the State of Michigan Department of EGLE 2024 Drinking Water State Revolving Fund project. The project is complete with punch list and closeout procedures underway.
4. Young Street from Chestnut to Brooks: Work scope includes water main replacement including non-compliant water service line replacement. The project was approved as part of the State of Michigan Department of EGLE 2024 Drinking Water State Revolving Fund project. The project has been postponed due to funding.
2024 Sewer Lining Project
The scope of work is sewer lining on sanitary and storm sewers at various locations. The project is complete.
2024 Bridge Projects
The scope of work is preventative maintenance repairs on the Gould Street bridge over the Shiawassee River and timber bridge deck replacement on the Oakwood Avenue bridge over the Shiawassee River. The project is complete.
2024 Chip Seal Project
The scope of work is double chip and fog seal on the following streets:
· Clinton from Shiawassee (M-52) to Michigan;
· Genesee from west end to Michigan;
· Cass from Shiawassee (M-52) to Ball;
· Ball from Cass to Howard;
· Howard from Ball to Washington (M-71);
· Milwaukee from Lyon to Cedar;
· Milwaukee from west end to Shiawassee (M-52); and
· Huron from Huggins to east end.
The project is complete.
2024 Sidewalk Replacement Program
The focus area for sidewalk replacement is the area bounded by Washington, Corunna, Abrey, and the Shiawassee River. The project is complete.
2024 Street Light Project
The scope of work is street light removal and replacement including new conduit and wiring on the following streets:
· Comstock from Water to Park;
· Washington from Water to Main (M-21);
· Main (M-21) from Washington to Park (south side only); and
· Park from Comstock to Main (M-21) (west side only).
The project was funded by ARPA funds and a RAP grant. The project is complete.
2024 Sanitary Sewer Repair Project
Work scope includes open-cut sewer repairs on sanitary sewers on W Exchange St, Herman St, Nelson St, and Ward St. The project has been awarded to Glaeser Dawes Corporation. Sanitary sewer repairs are complete on W Exchange St, Herman St, and Nelson St. Sanitary sewer repairs are in progress on Ward St.
Woodland Trails Sanitary Sewer Repair Project (2024)
The scope of work is repair of select sanitary sewer and manhole flow channels within the Woodland Trails Condominium. The project has been awarded to Apex Excavating & Underground. The project is complete with close out procedures underway.
CIS – James Miner Trail Connection Project (2025 & 2026)
Scope of work includes trail construction from the existing Clinton-Ionia-Shiawassee (CIS) trail termination at Smith Road to Chestnut St, bike lane installation on Chestnut St, Stewart St, and Washington St, James Miner Trail reconstruction from Hickory St to Oakwood St, and paving the Sam & Opal Voight walkway from Washington Street to the boardwalk. The project also includes rehabilitating Jerome St from Hickory St to Oakwood St. Design work is in progress by Fleis & Vandenbrink. Work is scheduled to take place in 2025 and 2026.
2025 Street Program
Projects planned for street resurfacing:
1. Howell Street from south end to Clinton. Work scope includes crush and shape with asphalt resurfacing. The project has been awarded to Glaeser Dawes Corporation with an April 21, 2025 start date.
2. Lynn Street from west end to Clinton. Work scope includes crush and shape with asphalt resurfacing. The project has been awarded to Glaeser Dawes Corporation with an April 21, 2025 start date.
Washington Park Utility Extension Project (2025)
Work scope includes sanitary sewer with lift station, water main installation, and street resurfacing on Wesley Dr from Water to Washington and water main installation on Washington St from North to Wesley. Design work is in progress by city staff and Tetra Tech. Construction is planned for Spring 2025.
2025 Sewer Televising Project
The following sewers are planned for televising:
1. Ament St between Lyon and Shiawassee (M-52) – storm sewer;
2. Bennett Field Dr between Lafayette and Hoyt – storm sewer;
3. Oliver St and Chipman St intersection – storm sewer;
4. Hickory St between King and Osburn – storm sewer;
5. Park Street between Osburn and Stratford – storm sewer;
6. King St and Dewey St intersection – storm and sanitary sewer; and
7. Sanitary Sewer Interceptor from Robbins and Main (M-21) to Hathaway – sanitary sewer.
Bids were received on November 19, 2024 with contract award scheduled for the December 2, 2024 city council meeting. The project is scheduled to begin January 6, 2025.
2025 Drainage Improvements Project
Work scope includes ditch cleaning on the North St ditch between Chipman and Hanover and on the Coventry Ct ditch. Bids were received on November 26, 2024 with contract award scheduled for the December 16, 2024 city council meeting. The project is scheduled to begin January 6, 2025.
EGLE Technical, Managerial, and Financial (TMF) Support Grant (2025)
Work scope includes investigating approximately 700 water service lines throughout the city. Water service lines will be investigated at the curb stop via hydro-excavating and inside the building at the water meter. Notification for scheduling investigations inside the building are in progress. Investigation at the curb stop is scheduled for Summer 2025.
2025 Water Main Replacement Project
Work scope includes water main replacement including non-compliant water service line replacement on the following streets:
1. Nafus Street from south end to Frederick;
2. Grace Street from Cedar to Shiawassee;
3. Young Street from Chestnut to Brooks;
4. Olmstead Street from Ward to Chipman;
5. Harding Avenue from Willow Springs to Hanover; and
6. Hanover Street from Harding to Riverside.
The project was approved as part of the State of Michigan Department of EGLE 2025 Drinking Water State Revolving Fund project. Design work is in progress with construction planned for late Summer 2025.
2025-2027 Water Service Line Replacement Project
Work scope includes noncompliant water service lines replacements targeting 600 locations within the City of Owosso over a 3-year time period. The project was approved as part of the State of Michigan Department of EGLE 2025 Drinking Water State Revolving Fund project. Design work/planning is in progress with construction planned to commence in late Summer 2025.